Hello
I have just started using Advanced Roadmaps in Jira for the past 2 months and created a Roadmap which goes across 4 Jira Projects / Boards. My question is around how the roadmap gets updated. As teams work on their tickets and some items take longer than originally planned, how come the Roadmap doesn't update automatically to reflect the "actual progress"? I may be confused but the only way I see the Roadmap adjusting is if I go in Advanced Roadmap and manually update the dates for the items that have changed. Is this correct or am I missing something? Can you please help clarify how the Roadmap dates should get updated in the plan or do I need to manually update the dates for the epics based on what the development teams are doing real time.
Thanks
- Val
Hi Val,
To show the epics or parent issues dates based on their children, you need to enable Roll-up Dates in your plan View settings. Note that, Advanced Roadmap does not update the epics date fields value in the Jira ticket, but it visualises them in the roadmap and also field sections.
Regards,
Sara
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.