Advanced agile roadmaps: using the Due Date as Target End but no change in map.

Rik007
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 18, 2021

Hi there,

Our organization just recently bought Advanced Roadmaps so we are in the initial phase of  how to implement and use this product for our teams. Following the documentation we learned that target start and target end date in the plan can be adjusted and once done the header description would change accordingly and show a date lozenge:

Expected.png

We change the Target end to show the Due Date. So we expected that the Due Date would show up instead of Target end. with the lozenge. Unfortunately nothing changes:

Result.png

What are we doing wrong?

Thank you for your assistance in advance. 

Rik

 

1 answer

0 votes
Jacob Vu
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 23, 2021

Hi @Rik007

You should be able to adjust the filter columns if you click the 3 dots that I circled in the image below:

Screen Shot 2021-08-23 at 6.38.01 PM.png

Hope that helps, let me know if it doesn't.