Agility Board - How to review and report on completed sprints

Edwin Ng
Contributor
October 10, 2018

Hi. Just started using an Agility Project for my team and am trying to review recently completed sprints.  

Is there a way a way of doing this easily as the traditional reporting capability is missing for Agility Projects.

2 answers

1 accepted

0 votes
Answer accepted
Edwin Ng
Contributor
October 13, 2018

Had a chat with Jira support and found a way to get the info I'm after using Search -> View All Boards, Filters, Dashboards or Projects -> Select Filters and I can query my agility as well as other projects

0 votes
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 10, 2018

Hello,

Go to the project settings -> Features and turn on the Reporing feature.

Edwin Ng
Contributor
October 11, 2018

Already done that but unfortunately there are only 2 reports available Burn Up and Velocity both which are not suitable and there is no way to customise them,

I want to be able to review the list by team member. How do I do that?

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 11, 2018

Ah, ok.

Then you can not add additional reports to a next-gen project. If you need reports from a "classic" project, then you should create a classic project

Edwin Ng
Contributor
October 11, 2018

Thanks.  Do you know if it is possible to do a report of tickets across multiple projects including next-gen and classic?

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 11, 2018

I am not sure, what you mean, but most reports accept a filter as a parameter. You can choose data from different projects in this filter.