Auto populate dates in Advanced Roadmap

Deleted user January 11, 2021

Hi

 

Each of my subtasks have estimates - but dont have start dates and due dates. Is it possible for the Advanced Roadmap feature to pull from the task estimations field and populate that in the Roadmap. For examples I have three tasks

SUB Task 1 - 2 days estimated

SUB Task 2 - 3 days

Sub Task 3 - 1 day

My total days for that story = 6 days (assuming each blocks the other)

Can those 6 days auto populate in the advanced roadmap for that story based on the task estimation? 

 

1 answer

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 11, 2021

Hi @[deleted] 

I believe the items on the roadmaps appear based upon the Start Date and Due Date fields.  Have you considered using Automation for Jira to set those fields based upon the estimates?

Please take a look at this documentation for more information:

https://support.atlassian.com/jira-software-cloud/docs/automate-your-jira-cloud-processes-and-workflows/

https://www.atlassian.com/software/jira/automation-template-library#/label/all/1453


Best regards,

Bill

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM Trial
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events