I've created a project, 4 epics, several tasks inside, and added dependencies, and time estimations. 
When I launch auto scheduling it starts some of the epics simultaneously with the first epic and shows it as a problem (which is). 

In settings dependent tasks can't go simultaneously.  

1 answer

0 votes
Brant Schroeder
Community Champion
June 12, 2025

@imurashka.v welcome to the Atlassian community

You have negative days on the blocker.  This means it could possibly start at the same time depending on duration.  