Hi Community,
On the way of automating my board, I have been trying one thing that is for now not working yet but am sure the issue is in a small detail.
In short, I have Issues with Issuetype "Task". I want to automate:
Is anyone able to help out?
Thanks a lot
Hi @bill,
Thanks for your Reply. Good point, here´s a screenshot of what I have right now.
Unfortunately, it does not work yet and returns nothing, something is wrong.
The documentation always states "now" as for today as reference. I would like to take as reference the Due Date from the parent task and then calculate with MinusBusinessdays.
Anyone can spot the mistake?
Kind regards,
Mourad
For a question like this, please post an image of your complete automation rule, images of any relevant actions / conditions / branches, an image of the audit log details showing the rule execution, and explain what is not working as expected. Those will provide context for the community to offer ideas. Thanks!
Until we see those...
What you describe is possible using the date time functions, specifically including the function plusBusinessDays(). Please look at this documentation to learn more:
https://confluence.atlassian.com/automation/jira-smart-values-date-and-time-993924864.html
Kind regards,
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.