Hello there
I am trying to create a automation rule that generate a subtask called 'QA' when an issue is moved to the Active Sprint and it doesn't already have a subtasked called 'QA'.
So the trigger is the change of the Sprint, and the conditions are:
1. the (new) sprint is the currently Active Sprint
2. there is no other subtask called 'QA' under that issue
The action is to create a new subtask called 'QA'.
I've created the below rule and it didn't work. It generated a subtask called 'QA' in the Active Sprint even though there was one under the issue already.
Please share your thoughts.
Thanks
Hi @mlangtry ,
Welcome to the Atlassian Community.
In a similar use case I used a Related issues condition instead of a Compare two values. Is this an option for you?
Regards, Marco Brundel
Thank you so much @Marco Brundel ! It works!