Hello,
I have 3 different epics. I want to automation the transition of the status of 3 US (1US by Epic).
Example : when US1 and US2 are in status "Done" I want that the US3 has automatically the status "In Progress"
Thank your for help
Hi @Ines Barhoumi and welcome to the community!
It is absolutely possible to transition "US3" when other issues transition to Done by leveraging a branch. However, you'll need business logic to define when this should occur...
US1 and US2 transitions to Done and there are 3 other user stories under that epic. How is your rule supposed to know which story is US3 (or US1 and US2 for that matter)?
Hi @Mark Segall
Thanks for your answer.
I use a link between US : US3 "has to be done after" US2And US1
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In that case, you could do something like this:
Note - I used "is blocked by" because I don't have "has to be done after" in my environment so just make the appropriate correction there.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.