Automation rules based on Status of US

Ines BARHOUMI April 11, 2022

Hello,

I have 3 different epics. I want to automation the transition of the status of 3 US (1US by Epic).

Example : when US1 and US2 are in status "Done" I want that the US3 has automatically the status "In Progress"

 

Thank your for help

2 answers

1 accepted

1 vote
Answer accepted
Mark Segall
Community Champion
April 11, 2022

Hi @Ines Barhoumi and welcome to the community!

It is absolutely possible to transition "US3" when other issues transition to Done by leveraging a branch. However, you'll need business logic to define when this should occur...

US1 and US2 transitions to Done and there are 3 other user stories under that epic.  How is your rule supposed to know which story is US3 (or US1 and US2 for that matter)?  

0 votes
Ines BARHOUMI April 11, 2022

Hi @Mark Segall 

Thanks for your answer.

I use a link between US : US3 "has to be done after" US2And US1

Mark Segall
Community Champion
April 11, 2022

In that case, you could do something like this:

2022-04-11_08-08-31.png

 

Note - I used "is blocked by" because I don't have "has to be done after" in my environment so just make the appropriate correction there.

Ines BARHOUMI April 11, 2022

Yes, i will try it !

Thanks a lot 