Automations: add label when status has changed in active sprint

Jolien Ryckaert
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 5, 2025

Hi,

I want to give a label to all issues that have been transitioned to a certain status in the active sprint.

This also means that the label should be removed from the issue when the next sprint starts. 

  • Trigger: when the issue is transitioned to "testing in progress"
  • Label: "dev_done"

Can this be done with Automations?

Kind regards,
Jolien

 

 

1 answer

0 votes
Sebastian Krzewiński
Community Champion
February 5, 2025

Hi @Jolien Ryckaert 

 

Yes, you can do this via automations. Basically you did this role in your description.

 

Regards,

Seba

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 6, 2025

Hi @Jolien Ryckaert -- Welcome to the Atlassian Community!

Adding to Sebastian's suggestion:

You would need a second rule to remove the label later...either when the current sprint completes or when the new one starts.

To get you started on creating your rules, please refer to these documentation and example sources:

Kind regards,
Bill