Basing Tempo budget/folio on scope not avails.

Kurt Wimberger
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 2, 2021

Hi all, not sure if this is the board for this question, but I am using tempo budgets. I can use full EVM just fine, and I typically base my cost estimates on the number of developers and the % of their availability during the schedule. 

Unfortunately not everyone likes this method. I have been asked to base the Folio cost estimates on just the scope (weeks/days/hours) of the project. Is there a way to do this? I can't figure it out.

 

Thanks.

2 answers

0 votes
Alexander Eck [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 7, 2021

Hi @Kurt Wimberger ,

yes you can do this by adding resources to your planned costs for a time period and a allocation to the project.

E.g. 4 developers for 50% of their time from the start towards the end of the Folio´s date

BR

0 votes
Josh July 6, 2021

Have you tried this EVM application?  

Aneto Project Accounting System with Earned Value Management 

 

Josh

Aneto