Hi all, not sure if this is the board for this question, but I am using tempo budgets. I can use full EVM just fine, and I typically base my cost estimates on the number of developers and the % of their availability during the schedule.
Unfortunately not everyone likes this method. I have been asked to base the Folio cost estimates on just the scope (weeks/days/hours) of the project. Is there a way to do this? I can't figure it out.
Thanks.
Hi @Kurt Wimberger ,
yes you can do this by adding resources to your planned costs for a time period and a allocation to the project.
E.g. 4 developers for 50% of their time from the start towards the end of the Folio´s date
BR
Have you tried this EVM application?
Aneto Project Accounting System with Earned Value Management
Josh
Aneto
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.