Does anyone know if the BigPicture Gantt chart can show tasks that have had their status set as "Done", within the last 3 months? If so, how?
I don't want to show tasks that have been completed on my Gantt chart, but think it would be good to be able to show the ones that have been recently completed.
Hi Sandeep
You can go to configuration of your BP program and create a quick filter as JQL resolved >= endOfDay(-30) , which will narrow down the tasks to the ones closed in the last 30 days.
Hi Daniel,
Thanks for this, helps me narrow it down... is there a way to include these with all other tasks?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sandeep
Yes, you can write your JQL to define whatever the scope you want to see.
for example, resolved >= endOfDay(-30) or status != closed, which will return issues closed within lats 30 days and the issues not closed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you can also add the Resolved field to your perspective so you can see the date it was closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.