Hello!
I have two bugs that are marked as done and are in a state that is green in the workflow, but every time we close out an active sprint, they're moved to the next sprint, even though they're done. What could be causing this? I don't think the problem is their resolution, because I have other unresolved bugs that are not included in the next sprint.
Attached is a screenshot of the bug with identifying info redacted.
Hi @Ashley Freeman,
If the status is not mapped to the right most column then the sprint take it as a undone issues and move it to the next sprint or to the backlog. Add the Done status to the right most column in sprint board
Go to Board --> configure--> columns and add the status to the right most column