Burndown chart not updated when the Sub Tasks and updated with logging work

Nishant March 29, 2022

Burndown chart is not getting updated as Sub tasks are updated with remaining efforts/estimates in hours. Ideally as soon as the sub tasks are updated with remaining estimates, it should reduce the estimate of the parent task as well as the Burndown chart should also be updated with this.

In Jira the burndown chart only gets updated when and only if the User Story/Task is marked resolved which is giving a wrong picture in reports.

please do suggest the solution for the same.

 

2 answers

1 vote
Fabio Racobaldo _Herzum_
Community Champion
March 29, 2022

Hi @Nishant ,

unfortunately, there's no way to have your estimate at sub-task level impact burdown chart. Estimation should be based just at parent side.

Hope this helps,

Fabio

Nishant March 31, 2022

Thanks for the response, basically it is a limitation in Jira, hope in future releases there can be a link made between Tasks - Sub Tasks in terms of effort spent across similar to other tools like Agile Central, Urban Turtle etc.

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 31, 2022

It's not a "limitation", it's just supporting Scrum properly.

You should not be doing sprint estimates on non-sprint items such as sub-tasks.

0 votes
Suvradip Paul
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 29, 2022

Hi @Nishant ,

Thanks for posting and welcome the community. I hope you are using Company Managed Project , please confirm if that's not the case. I would like to request you to check board column status mapping also for the above please check that remaining estimate and time spent is enabled in that board. Please go through this tutorial article - https://www.atlassian.com/agile/tutorials/burndown-charts and this documentation - https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-burndown-chart/.

Please let me know and accept the solution if it has solved your purpose.