Hello
I'm currently working on Jira. On one of my project (named project1), the button "create sprint" is missing on the backlog view. This button is here on another project (named project2)
I'm project administrator on both project.
On configure board, filter query is present (project = project1 order by rank asc), and ranking too (Using Rank). It seems have the same configuration as the project2
I can see the sprint field on each ticket of project1 and project2. But on project1, I can fill it with the sprint's name of project2. Maybe a missing configuration ?
Any idea ?
Best regards
Ok, I found the issue : my board was in Kanban and not in Scrum (and I wasn't aware than you can't create sprint in Kanban. Now I know :) )
Thanks a lot :p
Check the permission scheme in the second project, do you have the manage sprints permission?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Thank for the answer
I have the manage sprint permission (as a personn and as a group. I try as a group only or as a person only, no change)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.