Can I add links or fields to the data displayed on Sprint board cards? I have subtasks that contain links to the parent issues (stories) and vice versa, and I'd like these links to be displayed on the Sprint board cards.
Hello @Phil Bustin
Are you working with a board for a Team Managed project or a Company Managed project?
You cannot change the fields that are displayed on cards in an agile board created automatically for a Team Managed project.
As @Ditte Simard mentioned, you can add to the fields that are displayed on cards in an agile board for a Company Managed project. You can add up to three fields.
In a Company Managed project's agile board the subtasks should display indented under their parent story, if the subtasks are within scope of the board's filter. But there is no option to list all the subtask issue keys on the parent issue card, as that is not a "field" provided by Jira.
You can add "Parent" to the cards, and that will display the Summary of the parent issue on the Subtask cards. However, you cannot specify on which cards that field will display so it will display on all cards. If there is not a value for that field for that particular card then it will show "None".
I realized after I posted this that the sub-tasks are indeed displayed within a header showing the parent, and that's great.
I believe he project is company-managed, so I will try the card layout. Thank you both.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Must be a Team-managed board, because although I was able to select 3 fields, they didn't appear in the cards. Just for fun, where do I confirm the managed property of the board?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you look at the bottom of the navigation panel on the left you will see a statement telling you if the project is Team Managed or Company Managed.
It must be a Company Managed project because you would not even find the Card Layout option for a Team Managed project board.
In the Card Layout screen you have the option to add the fields to cards in the Backlog and a separate section to add fields to cards on the Board. Are you sure you added the fields in the section for cards on the Board?
Can you show us the Card Layout screen for your board, where you added the fields? And also show us the cards on the board itself?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Bingo! I wondered why there were two placed to add fields. If only I could read!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you go to "Configure Board" and then "Card Layout", you can see all the fields that you can add to your cards. In my Jira instance, I did not see a way to show the story/sub-task linkage.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.