I am not using GreenHopper
I have created a Scrum Board and pointed it at my project. The project had no sprints to begin with.
I have the following counts in tasks, sub-tasks, stories, epics, etc
They are broken down as
3 task
53 sub-task
4 story
4 new feature
11 improvement
6 epic
1 bug
55 technical task
The status counts are...
6 In progress
36 Resolved
1 Reopened
26 Closed
The plan board shows 23 items in the back log and of course nothing in the newly created sprint.
Q1: How can I create sprints and include historical activity, i.e. completed tasks?
Q2: Can I create a sprint that will include the tasks that are already in progress?
There are no limitations to statuses of Issues you include in your Sprints, but keep in mind that statuses mapped to the Done column won't show up in the backlog. If you want to see your Resolved and Closed Issues there and be able to add them to new Sprints, you'll need to move these statuses out of the Done column (or its equivalent in your Board).
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.