Baseline was a feature in the old version of Advanced Roadmaps (called Portfolio). What you can do is to use your own custom fields to capture this information. Something like Planned Date and Actual Date. When data is filled into these fields then you can always report on it later.
Ravi
Many thanks for the reply Ravi.
Does that mean that it can be shown on a Gantt chart, so it is easy to see how execution has(n't) changed versus the original plan?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Ian Smith
I think this is something you could do in Jira and not have to use Advanced Roadmaps for.
I'd use 'Due Date' and 'End Date' separately, meaning 'Due Date' is the planned date vs. End date which is the actual end.
I don't think there's an easy way to baseline in Jira or Advanced Roadmaps unfortunately.