Can't change epic start and end date on Gantt chart

David Doria
Contributor
October 26, 2017

With Stories, I can drag the left/right side of the bar that is displayed in the chart and the start/end date changes. With Epics, I can move the whole bar, but I can't extend or shrink the bar. How can I do that?

Thanks,

David

1 answer

1 vote
Piotrek Romanczyk [SoftwarePlant]
Atlassian Partner
November 3, 2017

Hello David,

 

In Program Configuration - Synchronization, please check 'off' the 'Recalculate Parents' option. This will allow you to modify tasks displayed on WBS Panel and on the Gantt chart that are already parents to other Jira issues.

 

Recalculate Gantt parents - disables extending and shrinking parent bars when on.pngRegards,

Piotr of SoftwarePlant