With Stories, I can drag the left/right side of the bar that is displayed in the chart and the start/end date changes. With Epics, I can move the whole bar, but I can't extend or shrink the bar. How can I do that?
Thanks,
David
Hello David,
In Program Configuration - Synchronization, please check 'off' the 'Recalculate Parents' option. This will allow you to modify tasks displayed on WBS Panel and on the Gantt chart that are already parents to other Jira issues.
Regards,
Piotr of SoftwarePlant