Hi,
I don't see any progress bars on any of my tasks.
I've updated the colours to show progress as a nice purple.
The descriptions says:
Issue Type: | ![]() |
Planned Start: | 09/Apr/14 12:00 a | ||||
Assignee: | XXX | Planned End: | 15/Apr/14 12:00 a | ||||
Original Estimate: | 5 days | Duration: | n.a. | ||||
Time Spent: | 0 days, 4 hours | Baseline Start: | 03/Apr/14 12:00 a | ||||
Estimated Time Remaining: | 4 days, 4 hours | Baseline End: | 09/Apr/14 12:00 a | ||||
Progress: | 10% | Due Date: | 09/Apr/14 12:00 a | ||||
|
The bar in the gantt doesn't show any purple.
Note also that the Duration says n.a. - any ideas why that is also? Some of our cases have duration, others dont'. This isn't related to progress - none of our tasks are showing progress.
Thanks
Jeff
Hi Jeff,
please use my JIRA to create a related support ticket: click on menu button with the question mark and select menu item "support request" in order to send an email with your problem and description including attached screenshots to illustrate that. Automatically, necessary information like JIRA version, Gantt-Chart version etc. are put into the email body for your convinience.
Kind regards,
Frank
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.