Can the due date for a scheduled issue automatically be set to the same work day every month?

Darius Sawyer
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 30, 2018

Hi,

I am scheduling a series of issues that are due at the same work day every month. Is it possible to set up a dynamic due date for this - perhaps a set number of days after the trigger is executed on the first of the month?

Thanks in advance.

1 answer

0 votes
Marc Jason Mutuc
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 30, 2018

A dynamic date would need to be based on another date. For example, you want the due date to be every Friday of the week, and you create your issues every Monday then you can have a dynamic date of Created + 4.

 

If you don't want to use add-ons you just have to bulk update it. If you are open to add-ons, take a look at ScriptRunner and JIRA Misc Custom Fields.