Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Can we make the rule when I change the status based on the status of link?

sangsub.kim
Contributor
October 9, 2020

I have two project.

A issue is belong to A project.

B issue is belong to B project.

 

I want to make the rule like the following.

Before changing Done workflow from A proj,   checking the link which is connect B issue status.

 

If B issue  is Done. A issue can be changed as Done.

But

If B issue is "in review", A issue can be not changed as Done.

 

How can I setup it?  I already checked "Add Condition To Transition", but I fail to find it.

 

 

 

1 answer

1 accepted

0 votes
Answer accepted
Chris Buzon
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 9, 2020

Yes, this can be done.  I'd suggest considering the JMWE (Jira Misc Workflow Extensions) as it has tools specifically for this.

https://marketplace.atlassian.com/apps/292/jira-misc-workflow-extensions-jmwe?hosting=cloud&tab=overview

This could also be done through JIRA automation, but it's a bit more work to set up and maintain.

Suggest an answer

Log in or Sign up to answer