Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Can you change what statuses count as "Done" for progress/velocity tacking?

Meagan Meyer
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 27, 2022

For example, the only statuses on our JIRA Sprint Board that count as "Done" are "Complete" or "Closed". 

We would like to have a "Ready for Integration" status count as "Done" because a lot of the time, we are ready to integrate but cannot do so because of a Business or vendor blocker. This messes with our velocity.

2 answers

1 accepted

1 vote
Answer accepted
John Funk
Community Champion
January 27, 2022

Hi Meagan - Welcome to the Atlassian Community!

Cards for Sprints are only considered Done or Complete if they are in the very last column on the board (far right), regardless of the status the card is in. So you need to map your "Ready for Integration" status to the very last column of the Sprint board. 

Ronny Ager-Wick
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 27, 2024

Can this be changed? This is a ridiculous way to define a task as done. We have multiple DONE statuses, such as "DONE" and "NOT NEEDED" and randomly picking whichever column we put on the right seems odd, and confusing.

If you find out during the sprint that something is not needed, then you don't want to delete the task, but keep it for historical reasons. It also doesn't make sense to mark it as DONE, as you didn't actually do it! Hence the "NOT NEEDED" done status.

Moreover, if you change which DONE column is furthest to the right, you also change the burndown/up and velocity of completed sprints! Why do you have the ability to select multiple "done" statuses anyway? Can you change this so that *all* done statuses counts as Done for sprints?

0 votes
AMIT GULATI
Contributor
January 27, 2022

I understand your concern but solution you are looking for is not correct.

 

Ideally, you should use the control chart to monitor the average time spent in 'Ready for Integration' status and try to reduce that by discussing with stakeholders.

 

To your original question, it can be achieved by mapping statuses to columns. Go to Board->Configure-> Columns to map statuses to columns

Achille Huet
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 2, 2024

"The solution [...] is not correct" => I don't agree.

Scrum teams should adapt their Definition of Done so that they are able to deliver increments within the  timeframe of a sprint.

Meagan should try to reduce time spent in that column, but if that solution has already been tried, then they can adapt their definition of done instead. There should always be some sort of business validation, but that could also be done by the PO instead of stakeholders.

Ronny Ager-Wick
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 27, 2024

Never mind, I just wasn't aware that you could put multiple statuses in one column - see the DONE column in the image below. This fixes the issue.

Just go to Board

Then Configure Board (which you can find under the ... menu)

Screenshot 2024-05-27 185507.png

Then you can do this:

Screenshot 2024-05-27 185039.png

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events