Hi,
The Card Layout "Progress" is not working for my Company managed project. It show None as a result instead of the sub-task bar.
Anyone faced the same issue before ?
Thanks !
Hi @Thibault Firmin and Welcome to the Atlassian Community!
You should go to board settings -> swimlanes and choose Stories. In this case subtasks will be under the parent.
I hope this information helps.
Regards,
Murat Seven
Hi !
Actually we use two views :
1) First one with swimlanes per Stories with the subtasks under the parents
2) Second one Swimlanes per Epics with Stories as cards
It is actually for the second one that I would like to display the Progress bar on the stories cards (the progress being based on the subtasks status)
But for some reason it shows "None"
Thanks for your help
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.