Hi , I need to know is there any way to change the Status of a Story From Inprogress to Sprint Done in a Closed Sprint
Hi, @Ashish.Srivastava1 ,
If you really needs to do this (not preferable), you need to reopen the sprint.
But as said it's not the way to go.
I would suggest to close the story then in the new sprint, as indeed normally you are asked in a popup what you want to do with the open issues.
Regards
Sven
When you close the Sprint that means you click on Complete Sprint, then you'll get a pop-up asking you to move the Open/In-Progress issues to either Backlog/Next Sprint where the action upon tickets can be taken place.
Thanks
Kinnera
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.