Hi there,

I was wondering if it's possible to configure the JIRA Agile Board, so that when I'm in 'Work' view, I can see the time tracking in the issue detail view on the right side. As it is now, I can only see it when I'm opening a certain task.

(edit: as far as I can tell it was configurable for the classic boards in the project template. this seems to have ceased to exist for the new boards somehow)

1 answer

1 accepted

0 votes
Answer accepted
Yves Riel _Okapya_
Atlassian Partner
October 29, 2013

Yes, this was possible with the Classic Board but not with the new Rapid Board. However, when the right-side panel is opened, you just need to click on the task to see its details. It is not that bad when you start using it.

Maximilian Nowak
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 29, 2013

Okay, thanks. At least I can stop now searching for this functionality;)