Dear Atlassian community,
Our team decided to use Story Points (SP) instead of Estimated Time (ET).
For the new stories, all the estimation would be based on SP - no problems.
For the old stories, as we have a lot of stories to update, we would like to pre-update the estimate by automatically adding a SP based on the ET (e.g. 4h = 1SP).
Would you have any idea how can I do that automatically ?
Thanks!
Hi,
Maybe you could csv export and import for this. Search for all issues that has to be updated, and export them to csv.
Then edit the csv and add a column for the story points. This should be possible using a formula in MS Excel for example.
Then you can re-import the csv. If you have the issue I'd in the csv, it will update the issues instead of creating new ones.
But be careful and create a backup before.
You can find more information here https://support.atlassian.com/jira-cloud-administration/docs/import-data-from-a-csv-file/
Hi, it worked perfectly, thank you very much!