Hi All
In the scrum board setting I do nto see an option wherein I can get to see the due/end date of the task/story as a visual on the board. any options to do show the same on the board ?
Regards
Preem
If you are on a company-managed project, You can go to Board settings > Card Layout and add the Due date field.
If you are on a team-managed project, unfortunately, that's not possible.
Here is how you can know which kind of project you are on.
If you want to move to a company-managed project type, this article can help you.
Hope this helps :)
Regards,
Bhanu