Do I need to estimate to use Portfolio?

Glynnis Kearney
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 13, 2018
I am trying to get a long term view of my backlog - essentially, I want to see my different initiatives spanning amounts of time that I set with start and end dates that I set. Do I need to do a bottoms up estimation in order to do this?

1 answer

0 votes
Walter Buggenhout
Community Champion
May 13, 2018

Hi @Glynnis Kearney,

Portfolio needs some kind of estimation or scheduling mechanism in order to calculate the schedule and demand.

If you have some (or all) items in your plan unestimated, you can use one of the following methods to work around that:

  • use default estimates for the story / epic / initiative levels
  • use target dates
  • use custom dates

For more details, check out this article in Atlassian documentation.