There is 1 un-pointed story.
There other stories that are remaining do not roll up to 124 points, and there are no estimates in the other estimate fields. The plan is set for story points.
Hi @Neil Wills
I would look at two things first:
The summary shows 46 estimated issues, is that the number of stories in all Epics we see in the Screenshot?
The solution was that the Epics had value and the stories.
The epic was automated to sum the points from its children.
With roadmap plans I can stop doing that.
Now to work with the teams to populate the epic story point with the estimate for the quarter to forecast the quarter, and remove it when you start decomposing stories.
We cannot solve having incomplete breakdowns for an epic, its agile after all.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.