We use 2 week sprints. Most start on Monday and end on Friday. Would the sprint length be 10 (the actual number of days sprinting) or 12 to include the weekend?
The sprint length should be 10 days, it is configured to only use 'working days' by default. you can change this if you'd like. To change it: