Does actual start date and end date update automatically in Jira Service Desk (Change Management)

Anu Ganesan April 21, 2022

In Jira Service Desk (Cloud) Change Management workflow, does actual start date and actual end date change automatically when status of Change ticket is changed to Implement and Completed respectively. If not, do we need to use Jira automation to change start and end dates?

1 answer

1 accepted

0 votes
Answer accepted
Gaurav
Community Champion
April 22, 2022

Hello @Anu Ganesan 

This is an interesting use case. Based on my experience, the fields are not automatically updated on a change of status for a change ticket.

But having said that, it is possible to create an automation rule which will help you achieve this.

Please feel free to let me know if you need any help in setting up the automation rule.

Kindly accept the answer if this helps.

Anu Ganesan April 22, 2022

If the actual start dates and end dates are not adjusted during the status change to Implement and Complete, how is the duration of the change is calculated?

Gaurav
Community Champion
April 25, 2022

@Anu Ganesan the change duration is being calculated based on the planned dates. The actual duration may vary depending on how the implementation goes.

Hope this helps :)

Like Anu Ganesan likes this