Hello,
I have a Jira program board with two levels : Initiatives and Epics.
When editing the increment for a team, we don't have the story point counters for the sprints while the epics issue type have a "story points" field filled.
However, we have it for the stories when using a program board with two levels : Epics and Stories.
How to have it also for Epics?
See below the two screenshots
Thank you in advance.
Hi Ruben,
Thanks for also raising this issue directly with us via our Support desk. Is the Team Planning view where there is no estimate field showing (image 1) the one we discussed that was based on a Kanban board?
Unfortunately, since Kanban boards have no Sprints to base these Program Increment columns on, Kanban boards in Easy Agile Programs do not have editable Sprint Estimates or Sprint names.
Kind regards,
Stephanie Seymour | Easy Agile
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.