Hi, I have a problem. I do not know how to configure the Gantt to take into account the employee's holiday.
Task 1, task 2, and task 3 are linked relationship 'has to be done after'. I would like to task 2 and task 3 moved beyond the holiday.
Can anyone help?
Thank you for all the answers.
Regards.
marta_holiday.png
Using latest version 3.2.6 of my Gantt-Chart or newer: if you already have issues within your JIRA and set some user's holidays afterwards, the issues being effected by that holidays will be updated automatically.
If you create a new issue having assigned an user, his/her holidays will be taken into account within all versions 3.x of my Gantt-Chart. Same while re-scheduling, which is forced e.g. by interactive issue linking or moving an issue, which is a predecessor.
Workaround in your case above: shift end date of issue #1 by one day (enable edit-mode by clicking on pencil icon and use drag'n drop on the right side of the bar) and then shift back to the original date to force a re-scheduling. Does this work for you?
Kind regards,
Frank
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.