Discovered my company has the Epic Sum Up widget and having a hard time with it and it's poor documentation.
I created the Epic Sum Up filter and Gadget option on both a Jira dashboard and Confluence wiki page. No matter what fields I select I don't see any sort of green bar to show tickets done or points done in tickets linked to the Epic. Help?
https://documentation.aptis.info/display/ESU/How+to+display+a+progress+bar+on+the+Dashboard+Gadget
Hi Bea,
I'm Johanna from the Epic Sum Up Marketing Team and I am happy to help you.
First off sorry about the documentation we're working on a complete new one.
How you do this depends if you're using Cloud or Server / Data Center. If you're on Server / Data Center you need to create a custom field first and configure it to show the Story Points progress bar. Just as described in here: https://documentation.aptis.info/display/ESU/How+to+display+a+progress+bar+on+the+Dashboard+Gadget
I can walk you through how it's done in a short call/video. If you're interested in that let me know.
Or you can contact our Support team here. Or at this email esu@aptis.support.
We're happy to help and answer any questions.
Hi Johanna,
I am having an issue seeing the IN PROGRESS statuses on my progress bars.
Is there a way for me to set this up?
Thank you
Valentina