I have my epic and 6 stories linked to the epic. I estimated story points for the 6 stories but not the epic. I started my 2 week sprint and have some clarification questions:
1. Should I have put estimated effort in for the 1 epic?
2. Should the epic have been included with the sprint?
3. If I am not including it in the sprint but the 6 stories have to be complete before I can close the epic how do I manage this one epic? Do I mark it as in progress or does it get changed automatically when someone begins a task on one of the 6 stories?
This may be down to personal preference. I've not found "proper" way of doing it. Maybe if Jira ever supports full nesting instead of just sub-tasks this might change.
On my team we keep the Epic in the backlog "pinned" i.e. just below the last story needed to complete it. The Epic always moves with that last story. If the order changes, then the epiv gets "pinned" to the last story.
Anything that happens to the last story happens to the Epic, i.e. moveing into sprints, being closed, being re-orderd on the backlog.
We don't estimate the Epic itself.
Hope that helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I'm curious how you 'pin' the Epic - is it just knowing which is the 'last' ticket for that Epic? or is there some way of relating them so they move together?
Gayathri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.