I've created a Portfolio Plan linked to two Jira Boards; both Jira Boards are using 'Time Estimation' rather than Story Points. I can see correctly in Portfolio the estimations made in Jira, but when I made some changes on the estimated value in Portfolio interface, they were not pushed to Jira; the Jira boards still show the original estimation.
Is there any way to ensure they stay in sync? I am doing something wrong?
did you commit your changes in your JIRA portfolio?
https://confluence.atlassian.com/jiraportfoliocloud/committing-your-plan-changes-828785217.html
Hope that helps!
Best wishes
Chris (STAGIL)
Hi Chris,
Indeed, I've commited the changes, but they changes didn't show on Jira boards. Any advice?
Thanks