Everit Timetracker: Do not "adjust automatically" for "Remaining Estimate"

Ewald_Ninaus March 10, 2016

If I add a Worklog directly in JIRA, it is possible to choose, if the "Remaining Estimate" ist adjusted automatically or not.

 

Now we want to use the Timetracker Plugin, but with this addon I have no configuration to change the default handling. Is there a way to disable this feature?

 

thx

2 answers

0 votes
Attila Bordás _Everit_
Atlassian Partner
December 19, 2016
Hello there,

I would like to let you know that we added Remaining Estimate adjustment options in the latest Timetracker versionYou can now choose in Timetracker Settings whether you want to display additional Remaining Estimate adjusting options.
Regards,
Attila
0 votes
Attila Bordás _Everit_
Atlassian Partner
July 6, 2016

Hi there!

Sorry for the late response and thank you for your feedback. You are rigth, Timetracker uses the default auto adjust on remaning time. We are planning to add the JIRA's other 3 option in the future.