When exporting to excel the original estimate, remaining estimate and time spent fields are not formatted correctly. using JIRA 4.4 excel 2010.
1 w in original estimate when exported to excel is represented as 144000.
40hrs * 60 minutes * 60 seconds = 144000
I'm not sure if that can be changed.
of course, it converts the weeks, days, hours to seconds for consistent exporting. Thank You
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can use the Better Excel Plugin to do this conversion for you. You can both use an Excel formula and Excel's cell formatting for this.
If you export time values frequently, it will save you from a lot of repetitive work.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There is a charge
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.