Gantt team board does not display my child's issues

elham April 27, 2023

Hi, 
I'm currently working on three different projects. The first project is project management, where I'm creating EPICs (Epics are large scale projects that are broken down into smaller tasks). The second project is software engineering, where I'm creating stories for developing the EPICs. The third project is testing, where I'm creating tasks to test the EPICs. When creating a Gantt chart from a project management board, it is not reflected the hierarchy of an EPICScreenshot 2023-04-27 at 16.17.20.pngThis Epic has 2 childs story task.

1 answer

0 votes
Ditte Simard
Community Champion
April 27, 2023

Are the Stories actually child issues of the Epics or are they linked in a different way?

elham April 28, 2023

 

 

Yes , they are Child of the EPIC

elham April 28, 2023

Screenshot 2023-04-28 at 10.09.06.png