A typical Sprint for us has about 150 tasks. Is there a way to resize the cards on the task board so that more of them are visible? We project his and only the task name needs to be readable.
Thanks,
Jim.
On the Agile/Greenhopper wall view, go to tools -> user preferences.
Under task board, there's a num field for issues per column, and parents per page.
Make that number as large as you need.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The List view shows more issues, especially if you select the User Preference for the issue only showing 2 lines.
Issues are colour-coded by issue-type, if you feel the List view makes it harder to see which are story or task then maybe try the User Preference for background colours on the issues. This can help when scanning a list to see issue breakdown.
http://confluence.atlassian.com/display/GH/Managing+your+User+Preferences
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jim
Just activate the "List" view.
Best regards
Thomas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
A list kind of defeats the whole Agile paradigm. Our folks want to see the stories and task disposition.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.