When I am on the Planning board view and I want to assign a version to an issue I drag the issue over to the fix version but nothing happens it just snaps back in place.
Anyone know whaty this would happen? Is there any conifiguration piece that I am missing?
Thanks,
Matt
It could be a permission issue. Check your JIRA permissions schemes and see if you have either the Close Issue or Schedule Issues permission. GreenHopper can be configured to use one of these two permissions.
http://confluence.atlassian.com/display/JIRA/Managing+Project+Permissions
Thank you. That was it. I suspected that. But when I looked deeper into what was happening I found it. The user didn't have Close permissions.
Thanks again,
Matt
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.