Assume there is a Story with 8 Story Points and with 4 sub-tasks under it. Those 8 points are being worked by different individuals and would take at least 4-5 days to close it. However daily there would be some progress on tasks and 1 task may get closed daily. If i see burndown chart, the chart would show a flat line for next 4-5 days even though some amount of work has been burnt.
How do i show that 25% or 50% of the story has been burnt?
Also,
How do you all use Story Points in Conjunction with "Original Estimate" and "Remaining Estimate"
Hi
Strictly speaking, what you've described is the correct view, because you are creating "value", and until the whole Story is complete, you don't have any value.
If you use time estimates for the sub-tasks, you could switch the Burndown to show remaining time estimate, then as work is completed on a sub-task, it will show less remaining time.
Hi @Warren -
How do I achieve the below reports, as we are using the JIRA Agile projects?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prasad, Did you figure out how to achieve the above? Even I am after something like this.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.