I'm not familiar with Agile but I received a question from a user regarding "Hour burndown charts". I've done a couple of research on the internet but couldn't find a clear answer.
It seems that the Hour Burndown Chart function is only available in the classic boards which are not supported anymore and which we are not using either anmyore. Is that completely true or is there a new way to obtain Hour Burndown Charts in the "new" Agile ?
Thank you for your answer.
Sorry, that's not true. Here's the answer I got from Atlassian in a support ticket:
Actually the new Burndown Chart is pretty similar to the Hour Burndown Chart from the Classic Board. The only difference is that the new Burndown Chart is sprint-based and not version-based. This chart can be found in any Scrum board in the "Reports" tab. There is also a "Sprint Burndown Chart Gadget" if you want to add it to your dashboard. You can see more information about the new Burndown Chart in the page below:
Hi Jennifer,
Unfortunately, this has never been resolved on my side either. The users managed to work without this feature.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have found the same thing and came looking for the answer here. Why has nobody answered in over 6 months?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.