We have recently switch to using Jira agile. After switching to scrum boards and using sprints there doesn't seem to be a way to say that release 2 includes sprint 4 and 5.
You could also - in Scrum|PlanBoard - drag and drop the issues to the right fixVersion.
Hi Julie
I would first want to question why you would want to do that. A sprint is a collection of stories that you ideally want to complete in a fixed period of time. It is not necessary that you will complete your sprint fully and that is exactly why we measure velocity.
If you had the option of adding all issues in sprints directly to fix versions then there would be a risk of adding an unfixed issue in the sprint to a release which is not ideal.
If you are sure that all issues in your sprint are fixed and ready for release what i suggest you is use JQL to search for the sprint and then do a bulk change to modify the fix version of all the issues returned from the search.
Hope this helps.
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.