Hey Guys,

 

I have many tasks in my roadmap but only 7 tasks are assigned to my Sprint-1

How is it possible to add more of them to sprint-1 ?

 

Thank you for any help

Bildschirmfoto 2022-08-04 um 10.31.00.pngBildschirmfoto 2022-08-04 um 10.29.44.png

2 answers

0 votes
Bharathi
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 4, 2022

Hello @Sandro Lainer,

You can drag and drop the issues from your backlog into the Sprint-1 or you can edit the "sprint" field to select the sprint value. Both options will help you to add the desired issues into the sprint.

Hope this helps!

Thanks!

0 votes
Fabio Racobaldo _Herzum_
Community Champion
August 4, 2022

Hi @Sandro Lainer ,

welcome to the Atlassian community!

Could you try to add Sprint field to your plan view? You should be able to select sprint for each issue in your list.

Immagine.png

Hope this helps,

Fabio