By default, the Timeline in Jira Board uses “Start date” and “Due date” as time fields. I need to replace them with our custom fields.
How should I configure this?
Hi @Xiaowen Chen ,
Welcome to the Atlassian community!
Unfortunately, the Jira board Timeline view (like the one shown in your screenshot) is currently hardcoded to only use the following system fields:
Start date
Due date
You cannot configure it to use custom fields in place of those at this time.
[JRACLOUD-91648] Allow Jira Board Timeline to use custom Start and End Dates - Create and track feature requests for Atlassian products.
If you want to use custom date fields in your timeline, please use advanced road maps.
Thanks,
Sanam