How can I create a board similar to this one, with a two tiers?
http://blog.crisp.se/henrikkniberg/images/KanbanVsScrumCoverPic.jpg
The Development column has a WIPL of 3, the sub columns of Ongoing and Done inherit this limit.
Hi David,
GreenHopper doesn't really have the ability to have subcolumns. You would have to define a separate column for "Ongoing" and "Done". Would that work for your situation?
-Simon
There is a related issue: https://jira.atlassian.com/browse/GHS-9807