Hy All
When i close mi sprint I can choose if I want to I have them in the next sprint or not. If I choose that the stories are moved into the next sprint unfortunately the stories are showed random in the next sprint backlog. Do you know a possibility or a function that sets the remaining stories at the top of the next sprint backlog automatically?
Thank you for your help!
Giulia
Hello @giulia.iannone
the position of your tickets in the backlog should be based on their rank. The rank is a global attribute that holds a unique value for each issue. The fact that other issues are ranked higher at the end of your sprint means, that the priorities were changed by some people.
By default, if you were to take the highest ranked issues and started a sprint, they would return at the highest position of your sprint backlog at the end. Such an automation would cause quite a ruckus to people who try to plan their backlogs. I'm sorry for the disappointing answer, but you should not do this.
You can create a card color to highlight all issues that have been in a sprint before, to make sure you are not missing any of them, or a quick filter.
Cheers,
Andrej
Thank you very much for your information. That helps! I will test it with Colours. Greetings!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.