I would like to add a project flag that dictates whether a project is Capitalized or Non-Capitalized. More importantly I need this to carry forward to add products such as tempo so I can run timesheet reports based on capitalized work vs non-cap work. I know I can add to any given story or task a custom field for this but at the project level I would also like to be able set this kind of field for reporting purposes. Suggestions?
The question is not whether a project is capitalizable or not, but what phases of the project can be capitalized. Research/planning is expensed, the implementation phase can be capitalized, later/ongoing maintenance is expensed.
Besides the project phases, you need the cost that is essentially the workforce (read you need to quantify time spent on that work).
Could you use project category for this? Or are you already using it?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.