Tanvi Jain December 14, 2023

I want to use Advance Roadmaps to know if any feature or  epic is on track/off track/at risk?

In the Atlassian video "How Atlassian Uses Advanced Roadmaps" - I saw a field "How are we tracking?". This is exactly what I'm looking for. How can I start using this functionality?

jira-project-status.png

2 answers

1 accepted

0 votes
Answer accepted
Mayuresh Kamble
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 14, 2023

Hi @Tanvi Jain ,

  1. Create a custom field of type Select List (single choice)
  2. Add options like
    1. On Track
    2. Off Track
    3. At Risk 
  3. Add the new field to the custom field option in the Plans settings > Source Data.

Once this is done you can add the field using dropdown in the Roadmap and in the view settings you can sort them by the Color by option .

Regards,
Mayuresh

Tanvi Jain December 17, 2023

Thanks @Mayuresh Kamble ! How will the value of this field be populated?

Mayuresh Kamble
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 17, 2023

You will need to set it manually

Tanvi Jain January 8, 2024

Thanks @Mayuresh Kamble ! Is there a way to configure working days in JIRA Advanceds Roadmaps? I know it can be done on boards, but not sure about Timeline view.

Mayuresh Kamble
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 8, 2024

That option is not currently available.

You can vote/comment on the change request for it here:

https://jira.atlassian.com/browse/JSWCLOUD-25523

Like Tanvi Jain likes this
Tanvi Jain January 11, 2024

Done.. thanks!

Mayuresh Kamble
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 11, 2024

Please accept the answer if you find it helpful

Thanks!

Tanvi Jain January 14, 2024

@Mayuresh Kamble Is it possible to do Capacity Planning on Advanced Roadmaps for Kanban based project?

Mayuresh Kamble
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 15, 2024

Yes the Capacity Planning can be done for Kanban projects also as mentioned here also you can refer to this Post for more information regarding the same.

Regards,
Mayuresh

1 vote
Pramodh M
Community Champion
December 14, 2023

Hey there,

Please find the webinar link here to get started with Advanced Roadmaps

There's also a paid course that dives into each concept- Link and finally documentation

Thanks,
Pramodh

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
TAGS
AUG Leaders

Atlassian Community Events